A tracker’s list of Idaho data center projects

Ready to paste into a message or email.

Copy this address: https://idahowaterstatus.com/research/sources/SRC-000065

What this source tells us

A canceled plan in Pocatello makes up $2.6 billion of the $4.6 billion total for nine Idaho projects.

ServerCountry, a website that tracks data centers, lists nine Idaho projects. Its totals come to $4.6 billion in announced investment and 954.65 megawatts of power capacity. Four entries are listed as under construction, two planned, two operating and one canceled. Those totals include the canceled project: Lex Developments in Pocatello, at $2.6 billion and 100 megawatts.

The biggest by power is Diode Ventures’ Gemstone Technology Park in Kuna, planned at 700 megawatts. The site lists Meta’s 60-megawatt Kuna data center as under construction. The two operating sites are small. The Federal Bureau of Investigation’s Grey Wolf center in Pocatello is listed at 5.4 megawatts, and ark data centers in Boise at 1 megawatt. Other entries are in Boise, Nampa and Idaho Falls, plus one with no stated location. The table lists no water use, and megawatts alone cannot tell you how much water a project will need. These are the website’s own entries, so check them against operator, planning and utility records.

Agency or publisher page read · Summary checked November 6, 2026

How this summary was checked

Read the original source (opens a new tab)

Source details and citation information

Record reference: SRC-000065

Catalog title: Idaho data centers investigative sweep - public reporting, trackers, and operator pages

Needs review
Dataset
Overview
Owner
Multiple (BoiseDev, Data Center Dynamics, East Idaho News, ConstructConnect, Server Country, Baxtel, Data Center Map, DOE, INL, operators)
Source authority
Tier 4 - Stakeholder/media/commentary
Source type
Dataset
Period covered
Announcements 2019-2026; per-record evidence dates, reviewed through 2026-09-28
Publication date
Unknown
Geography
Statewide Idaho
Update cadence
Irregular
Water accounting type
Unknown
Provisional status
Mixed
Caveats & use
Primary use
Data centers layer on the investor infrastructure map
Known caveats
Nine supported approximate placements; Ark and Centeris current qualifying operation remains unverified and both stay excluded. Deep Atomic has no verified assigned site/county and stays a proposed research record without geometry. P22 treatments approved September 28: Aalo–Crusoe proposed at the approximate Aalo-X campus representative, unknown data-center MW; Lex proposed at a two-parcel representative, prominent permit-denied qualification. These points are not surveyed building footprints. Lex final September signed order/subsequent disposition remains unverified; up to 100 MW is requested power. Aalo 10 MWe is reactor output, not data-center load. FBI/C3 address/county-source limitations remain. T5 operating responsibility and initial 2.25/2.5 MW reports remain unresolved. ValorC3 future phases are not counted separately. Source review does not establish current operations for withheld records, water sufficiency or complete statewide coverage.
Human review
Required
Claims citing this source

No claims cite this source yet.