Dixie Drain phosphorus removal plant, a case study
Ready to paste into a message or email.
Copy this address: https://idahowaterstatus.com/research/sources/SRC-000236
What this source tells us
Boise pulls phosphorus out of a farm drain 40 miles downstream to offset costlier upgrades at its sewer plants.
Dixie Drain is an irrigation channel, built in the early 1900s, that returns farm water to the lower Boise River. It sits about 40 miles downstream of Boise’s two wastewater plants. The U.S. Environmental Protection Agency’s case study calls it the largest tributary source of phosphorus to the river during irrigation season. When Boise’s discharge permits added strict phosphorus limits, they also included building and running a removal plant on the drain. The facility opened in July 2016. Chemicals called flocculants bind the phosphorus into clumps that settle in a basin. The clumps are dredged out, and the treated water returns to the river.
Boise’s permits require removing at least 25 pounds of phosphorus a day from May through September. At full capacity in that season, the facility can treat up to 130 million gallons a day. It can remove more than 140 pounds of phosphorus a day. Those are capacity figures, not measured yearly results. The case study links to the City of Boise’s Dixie Drain project page for more detail.
Original document read · Summary checked November 6, 2026
How this summary was checked
-
One-page EPA nutrient-reduction case study: project rationale, July 2016 start, treatment process and capacity-qualified figures.
Open the referenced material (opens in a new tab)
Read the original source (opens a new tab)
Source details and citation information
Record reference: SRC-000236
Catalog title: Nutrient Reduction Case Study: Dixie Drain Phosphorus Removal Facility
- Owner
- EPA (Federal agency)
- Source authority
- Tier 2 - Official interpretation/operations
- Source type
- PDF report
- Period covered
- Undated case study; reports operation beginning July 2016
- Publication date
- Unknown
- Geography
- Dixie Drain / Lower Boise River
- Update cadence
- Irregular
- Water accounting type
- Discharge,Permit/compliance
- Provisional status
- Mixed
- Primary use
- Implemented project, agency account
- Known caveats
- Full-capacity treatment/removal figures are capacity statements. EPA benefit language is not a controlled outcome study or current DMR total. Use newer permit and monitoring records for dated terms/results.
- Human review
- Required