Moving Mountain Home Air Force Base to river water
Ready to paste into a message or email.
Copy this address: https://idahowaterstatus.com/research/sources/SRC-000425
What this source tells us
The state finished a $32 million intake and pipeline in 2025 to bring Snake River water to Mountain Home Air Force Base. The full system is scheduled to run by 2027.
The state’s project page says the base currently relies on groundwater from the declining Mountain Home Plateau Aquifer. It calls that supply unsustainable and says there were concerns about nitrate contamination. A 2016 water supply report outlined using water from C.J. Strike Reservoir instead. With support from the governor and Legislature, the Idaho Water Resource Board bought senior Snake River water rights from the Simplot Corporation. The board will keep those rights and deliver the water to the base under a water utility service agreement.
The state’s part was finished in 2025: an intake, a raw-water pump station and 14.4 miles of pipeline, built under budget for $32 million. The Air Force is still building a treatment plant and storage tanks to receive the water. The page, last updated September 14, 2026, says the whole system is scheduled to operate by 2027.
Agency or publisher page read · Summary checked November 6, 2026
How this summary was checked
-
Project overview updated September 14, 2026: water-right acquisition, completed state works and operational schedule
Open the referenced material (opens in a new tab)
Read the original source (opens a new tab)
Source details and citation information
Record reference: SRC-000425
Catalog title: Mountain Home Air Force Base Sustainable Water Supply Project
- Owner
- IDWR (State agency)
- Source authority
- Tier 2 - Official interpretation/operations
- Source type
- Webpage
- Period covered
- Current gateway inspected September 28, 2026 describes 2025 transmission completion and operation scheduled by 2027; older fact sheet expectations differ
- Publication date
- Unknown
- Geography
- C.J. Strike Reservoir to Mountain Home Air Force Base; not the city public water system
- Update cadence
- Irregular
- Water accounting type
- Unknown
- Provisional status
- Mixed
- Primary use
- Basin source selection and evidence
- Known caveats
- Gateway says transmission completed in 2025 for $32 million, while older brochure projected July 2025/$40 million and treatment commissioning in 2027. Project-specific current treatment acceptance, deliveries and pumping offsets not independently verified. Resolution 11 recital is broader than gateway status. No present base water-quality result or current CCR obtained; nitrate concerns remain attributed historical project motivation.
- Human review
- Required