Moving Mountain Home Air Force Base to river water

Ready to paste into a message or email.

Copy this address: https://idahowaterstatus.com/research/sources/SRC-000425

What this source tells us

The state finished a $32 million intake and pipeline in 2025 to bring Snake River water to Mountain Home Air Force Base. The full system is scheduled to run by 2027.

The state’s project page says the base currently relies on groundwater from the declining Mountain Home Plateau Aquifer. It calls that supply unsustainable and says there were concerns about nitrate contamination. A 2016 water supply report outlined using water from C.J. Strike Reservoir instead. With support from the governor and Legislature, the Idaho Water Resource Board bought senior Snake River water rights from the Simplot Corporation. The board will keep those rights and deliver the water to the base under a water utility service agreement.

The state’s part was finished in 2025: an intake, a raw-water pump station and 14.4 miles of pipeline, built under budget for $32 million. The Air Force is still building a treatment plant and storage tanks to receive the water. The page, last updated September 14, 2026, says the whole system is scheduled to operate by 2027.

Agency or publisher page read · Summary checked November 6, 2026

How this summary was checked

Read the original source (opens a new tab)

Source details and citation information

Record reference: SRC-000425

Catalog title: Mountain Home Air Force Base Sustainable Water Supply Project

Tier 2 - Official interpretation/operations
Needs review
Webpage
Overview
Owner
IDWR (State agency)
Source authority
Tier 2 - Official interpretation/operations
Source type
Webpage
Period covered
Current gateway inspected September 28, 2026 describes 2025 transmission completion and operation scheduled by 2027; older fact sheet expectations differ
Publication date
Unknown
Geography
C.J. Strike Reservoir to Mountain Home Air Force Base; not the city public water system
Update cadence
Irregular
Water accounting type
Unknown
Provisional status
Mixed
Caveats & use
Primary use
Basin source selection and evidence
Known caveats
Gateway says transmission completed in 2025 for $32 million, while older brochure projected July 2025/$40 million and treatment commissioning in 2027. Project-specific current treatment acceptance, deliveries and pumping offsets not independently verified. Resolution 11 recital is broader than gateway status. No present base water-quality result or current CCR obtained; nitrate concerns remain attributed historical project motivation.