Suez Water Idaho’s master water plan for 2015 to 2065
Ready to paste into a message or email.
Copy this address: https://idahowaterstatus.com/research/sources/SRC-000559
What this source tells us
Suez Water Idaho found in 2016 that its water rights could meet forecast peak-day demand through 2058, then fall short.
Suez Water Idaho, the company now called Veolia Water Idaho, adopted this plan on September 23, 2016. It filed a corrected copy with the Idaho Department of Water Resources on April 28, 2017. The plan forecasts peak-day demand of 370.87 cubic feet per second (cfs) in August 2065. Cfs is a flow rate, and one cfs equals about 646,317 gallons a day. Simply adding up the company’s 125 water rights and entitlements gives 415.01 cfs. The plan then trims that total for combined rate limits (370.34), annual volume limits (350.58) and the months when each source can be used (330.58).
That leaves a gap of 40.29 cfs on August peak days in 2065. The plan says its rights cover forecast demand through 2058. In 2065 they still cover every day except August peak days. It calls 330.58 cfs a best case, since some exchange and flood-release rights vary from year to year. It expects to update the forecast over time and to need more water rights to close the gap. This plan is about water rights. A separate master facilities plan covers the physical facilities the company expects to build over 20 years.
Selected passages read · Summary checked November 6, 2026
How this summary was checked
-
Master-plan PDF pages 8,40 and45: forecast-update caveat, Forecast Table7 adjustments and Table11 seasonal/potential-availability qualifications.
Open the referenced material (opens in a new tab)
Read the original source (opens a new tab)
Source details and citation information
Record reference: SRC-000559
Catalog title: SUEZ Water Idaho Inc. Master Water Plan for the Years 2015 to 2065
- Owner
- SUEZ Water Idaho Inc.; filed with Idaho Department of Water Resources (Utility/operator)
- Source authority
- Tier 3 - Scientific/technical synthesis
- Source type
- PDF report
- Period covered
- 2015-2065 forecast; company adopted September 23, 2016; April 28, 2017 errata and filing
- Publication date
- September 23, 2016
- Geography
- Veolia Water Idaho; Boise and portions of Ada County; document-specific boundaries
- Update cadence
- Static / legal / historical
- Water accounting type
- Forecast
- Provisional status
- Modeled
- Primary use
- Mechanism / explanation
- Known caveats
- Water-rights planning model, not current firm physical capacity. Portfolio assumes exchange water availability at peak and does not establish present rights or commitments. Planning area is not a service commitment. January 29, 2016 version cited by SRC-000051 is not established as identical.